The Woolworths trolley bay, switchroom and tenancy storeroom slabs have been successfully poured with the precast panels scheduled to arrive next week with the structural steel to follow.

The new Norman Street car park entry sub base work is complete and, following on from the completion of the final stage of the structural demolition, the remaining civil works for the shopping centre extension have progressed well.