Works at the 5 Bond St project for client QIC are progressing well as the concrete structure continues upwards, with formwork now underway for Level 4.

Mobilisation of the perimeter safety screens is now complete, as the project looks towards the tower crane reaching its final height following the completion of the Level 4 suspended slab. Stripping of formwork to the lower floors has also commenced, enabling service trades to begin high-level rough-in works.

We’d like to thank our project team and valued subcontractors involved.